Buildings
and Facilities Task Force
Monday, April 7, 2025 - 9:00 am
Steve McNally - Chairman
Chairman McNally called this task force to
order at 9:00 am with the following in attendance: Matt Brassard, Chris Clark,
Robin DeLoria, Derek Doty, Ken Hughes, Steve McNally, Jim Monty, Favor Smith,
Davina Thurston, Ike Tyler, Meg Wood, Mark Wright, Mike Mascarenas and Jim
Dougan.
Also present: Dina Garvey, Andrew
Stanley, Nancy Page, Bill Johnston and Elizabeth Lee.
MCNALLY: Go Ahead, Jimmy
DOUGAN: I’ll let Andrew, start.
STANLEY: Ag and Youth Building, on site
work was completed this past month. The 4H Building was demolished and disposed
of. There was a new fuel tank installed in the basement of the existing Ag
Center and removal of an underground fuel storage tank at the former CCE
Building.
TYLER: I can see that far from here, but
do you have the location of the band building that is done there?
DOUGAN: That stays where it is.
TYLER: There’s plenty of room there?
DOUGAN: It’s going to be tight during construction,
but it stays there.
STANLEY: The birch tree is gone. We
relocated the files from the old fair office, in that one corner of the
building, upstairs. That’s where the construction office is going to be, right
there, the southeast corner of the building, I guess.
The contractor is planning to begin,
next month, a week from today.
DELORIA: Who is your GC?
STANLEY: Contact Building Systems, out
of the Malone area.
DOUGAN: They’re using a local site
contractor, Fuller Excavating and they’re supposed to start putting out their
erosion control and things like that by Monday, possibly toward the end of this
week.
TYLER: It’s hard to find people to do
that.
DOUGAN: It’s kind of light commercial
construction, so you’re right. You don’t get a lot of companies that want to do
that these days.
TYLER: Clerk of the works, did you find
somebody?
DOUGAN: We’re using Nate, from our
office, as our on-site guy every day. He’s mostly our eyes and ears, but we
expect with his limited amount of experience that Andrew and I are going to
have to be there a lot.
TYLER: Right
DELORIA: He seems pretty sharp.
DOUGAN: He is, but he could use some of
this experience.
STANLEY: Old Jail Demo; some temporary
gravel sidewalk along Treasurer’s Building is in progress. We still need to
reconnect the sanitary sewer that goes from the Old Sheriff’s Residence back to
the septic tanks, over here and we’re working on some design of sidewalks,
parking access and landscaped areas.
DOUGAN: We’ll bring back a couple of
options to this committee to take a look at. We’re doing that right now, we’re
supplementing the survey that we already have, adding all the utilities that
we’ve done a lot of marking on and try to build that in.
STANLEY: Frontier Town; we have received
bids for the first phase of the project. The low bidder was Bronze, which is
the same company that did the old jail, out here. The contract award is in
process. So, their bid came in at about $102,000.00.
MCNALLY: We were pleased with that,
their performance, correct?
STANLEY: Absolutely
MASCARENAS: They did a great job.
STANLEY: Fairgrounds; the former CCE
Building, roof replacement. Roof failure can be contributed to mostly lack of
proper insulation and ventilation. We have requested a proposal for design of a
insulation/ventilation system from AEDA. We’re working on that, there’s no
sense of putting new shingles on it unless we address the problem.
MCNALLY: Does it have rafters in that
building?
DOUGAN: It is rafters. If you drive by
you can tell that the cupula vents that area in the center of the roof pretty
well and so the shingles are nice bright red, underneath the cupula on both
sides and then on either other side there are they’re burnt right up.
MCNALLY: You’re never going to have
shingle last unless you have proper insulation and old buildings, it’s very hard,
after the fact to engineer a good ventilation system. The way to take care of
that is with spray foam insulation. It’s one and done, you do some cross vents
on it and spray in foam, it helps with, you know structure. So, you know, I
think we should really consider that when it comes to insulating that building.
STANLEY: Portable stage unit; bid
awarded and the purchase order was provided to the vendor in late January.
Anticipated delivery is 6-8 months, after the receipt of the purchasing order,
so July-September.
DOUGAN: The earliest will be July. We’ve
spoke to the vendor and it’s definitely won’t be constructed until at least
July. So, we’re asking for an update on that, we’re watching closely in part
for the fair in August.
STANLEY: The former Probation Building;
Phase 1, partial remodel of the first floor and the second floor, south side of
the building. We have a conceptual layout on the next page, interior demolition
of non-structural walls have begun by DPW staff. The asbestos survey is in draft
progress. They have come and taken samples, just waiting for the results and
the reports back on that. It does look like a portion of the flooring in
there, not knowing what’s under
everything, but the one area is more than likely going to be 9x9 asbestos
containing tiles.
So, we’ll need to finalize the layout.
DOUGAN: We’re going to bid all the
materials and we’re going to do what we can ourselves, once we see the asbestos
survey, we’re going to do what we can in that first phase ourselves and then
probably, we may use our term contractor, general contractor for a few things.
They’re much quicker at taping sheetrock and much quicker at doing acoustical
ceilings and a few of those things, but we think we can fit it in with some of
our own staff.
STANLEY: And the mini-split air
conditioning units have already been bid.
DOUGAN: it’s just a quick layout, we
kind of showed this last month, but right now we’re doing the southern end of
the building, closest to Treasurer’s and if there is asbestos flooring
throughout then we’ll do the removal as one project.
So, I just wanted to give everybody an
update. Every few months I try to, at this meeting, give you an update on our
other specifically budgeted projects for the year, even though a lot of them
are smaller. So, main complex; one of the specifically budgeted projects was to
redo the flooring and the paint in the mailroom, kind of to continue on what we
did a year ago in the main hallway. So, we bid and awarded the flooring, we’re
going to be continuing that vinyl into that area. We’re going to be replacing
the mailbox, probably relocating things a little bit to make it a little bit
efficient to go through there and Buildings and Grounds staff will be doing the
majority of the work other than the flooring.
Social Services training room; we’re
going to replace the flooring and the paint in there. We’re also going to
relocate all the wire mold data lines and electrical lines and install new
countertops along the outside walls. Clean that area up a little bit, but also
make it ready to be a swing space, as we need to start to tackle other parts of
Social Services. If we have countertops on both sides, Angie and her staff are
able to relocate small departments at a time as we need to start doing other
work in these areas. Again, flooring contractor already awarded with our
Buildings and Grounds Staff doing most of the work.
The main boiler loop; we have a lot of
controls issues in our main boilers here. The boilers are pretty good, but when
we get to this time of year, we have a lot of, the guys have to come and adjust
the boilers and controls, 2-3 times during the day. You know, if we have a cold
morning and then it hits 60°, everybody is super-hot in the afternoon, so Hugh
Harwood and our staff, designed a couple of things that change the loop
slightly. We’ve already ordered the materials, they’ve already been delivered
and the Buildings and Grounds staff is going to change out that piping, after
heating season is done.
We’re going to add one mini-split
cooling unit to the Board of Supervisors’ Chambers, just to, on those super-hot
July days, August days to just temper the space a bit. It really isn’t designed to completely handle
that room. It will also add a little bit of heat in the wintertime, again,
we’ve already bid the unit and awarded it to Mountain Valley Mechanical and
we’re awaiting the delivery, Buildings and Grounds is going to install that.
Real Property; same thing, the Real
Property Office has been cooled by window air conditioners, installed every
late spring and then pulled out late fall. That has caused some electrical
issues in there, especially when they’re trying to print up the big mailings.
It caused issues last year, so we’re going to install mini-split units there.
We’re actually going to lower the ceiling, as well, to make the area that we’re
heating and cooling that we’re trying to temper a little bit smaller. So,
mini-splits have already been awarded and we’ll do that, most of the work
ourselves, but we’ll have JFP do the acoustical ceiling to get that done,
quickly. That stuff will be done after
hours.
IT Air Handler; another budgeted
project, the supplier, is Hyde Stone, it was ordered in January, we’re waiting delivery
and then a combination of our folks who are going to tear the old one out and
then AD Thornton, our on-contract, mechanical contractor will get that
installed. We’ve got to customized the duct work which is why we’ve got
contractors.
The County Courthouse; the boilers, the
burners and the zone pumps, the zone pumps are all original from when it was
built in 1996 and the burners are needed to be upgraded, so we’re going to do
that work ourselves. We’ve already ordered the materials from Hulbert Bros.,
after heating season is over, we’re going to have one of our staff do them.
And Rooftop #10; we’re getting, we’re
reworking some of the controls again, over there to get away from proprietary
controls and our term contractor, Altech will be doing that work for us, again,
after heating season.
TYLER: Jim, you say that Buildings and Grounds are
going to be doing a lot of this work, do we have a full staff of employees?
DOUGAN: Our crews are full right now, our
crews are full right now. We were lucky enough, we got one person that left us
a couple of years ago, that was a pretty skilled electrician, pretty skilled in
a lot of things, came back, left us to go to work for State, New York State
DEC, the campgrounds and stuff, but he came back. Some of that was because of
you guys approving some the raises that we’ve had for the last few years and
some of the ability to keep their benefits based on years of service. So, he’s
back, we have a couple of other people that we think are fairly strong in HVAC
and I’ve got Hugh Harwood and got Andrew, here helping those guys. It’s not
necessarily going to be easy. We’re going through the schedule, again, this
morning, but I think we have a pretty decent plan to get it done.
Public Safety Building; things we’ve
been talking about, so we’re going to tackle the controls change out to get
away from proprietary controls on the boiler system, itself. We’ve got a
$135,000.00 set up there, Todd, Nate, Hugh are all doing what are called input
and output diagrams, right now and how they want things to react to each other
for the computer system and then we’ve got a contractor, under term contract
for climate who’s going to do that for us.
The Electrical Switch Gear; we talked
about that a few times. The goal this year is to know exactly what it’s going to
cost for the full replacement of that. So, we’ve set aside $100,000.00 this
year. out preliminary design is only $15,000.00, that’s where we are right now
in that preliminary design to change that out.
Then the Roof Top Units; which really
started this whole thing when one failed three years ago. We’re now going to
get back to preliminary design of those. It’s going to include the addition of
heat recovery in some areas of the building and getting away from those
proprietary controls. We just have a small contract for design right now, we
like to give it out in little bites. Hugh, Andrew, my guys up there are doing
what I call design management. We don’t let a contractor just run and give us a
design and show up at the end and roll out a set of plans and this is it. We
want to make sure it works for us.
Our Annual Mini-Splits; we’ve been doing
that for about 4 years now, just an annual mini-split replacement up there,
partly for our data rooms and some other areas and so those were already bid
and awarded, just waiting for them to show up and our Buildings and Grounds
staff, up there, will be installing those. The same thing with circulator
pumps, Buildings and Grounds staff will install them and we’ve already procured
them.
So, kind of a quick rundown, but these
were all specifically called out during our budget hearings last year, as
budgeted projects, so I just wanted to give you and update. I have done a lot
of ordering, early on to get the materials here and then as they get here,
we’ll start to phase in the work, distribute amongst our staff.
DOTY: Jim, I’ve just got like an
accounting related, like I like the fact that you’ve looked down the road and
envisioned what the total of a lot of these projects could cause, but you’re
phasing things as you go. My question is, say it totals a million dollars and
you’re going to need $200,000.00 this year, with you, Mike, does that stay line
item in DPW or does it convert to fund balance, so we’ve got to go through this
process again, next year?
MASCARENAS: So, what you’re really
seeing here is for many years now, we’ve been working on trying to get a level
on consistent budgeting that deals with our needs on campus. When we had those
horrible budget years, not that long ago, what was cut out every year was
operations and maintenance. That was the easy thing, we’re a government of
service.
DOTY: It’s like starting from zero every
year.
MASCARENAS: Right, so we have a level of
consistent budgeting. Jim, has X amount of dollars that we try to deal with
some of these reoccurring items on an annual basis. Those O&M items that
you know are going to hit you. The capital projects that the Board set up, is
kind of set up to be that fund that we can do some of those bigger one-time
expense deals that are going to happen on a reoccurring basis. So, we shouldn’t have to touch fund balance if our
planning is good, based on those two things. So, yeah, Jim’s doing a good job
with planning. His group’s doing a really good job with that and getting us to
a place where we can remain consistent, so we aren’t seeing big fluctuations in
budget numbers like we were seeing before. One year it would be $200,000.00,
the next year it would be a million. We can’t do that, let’s look at it over 5,
6, 7 years and figure that out.
DOTY: So, I guess I should ask the
question a different way, does the County have a fund balance policy where at
the end of the year, you’re only retaining, 30% or 35% of fund balance and then
you’ve got to reallocate? I guess that’s what I am concerned, because he’s done
enough homework now that there’s projects are kind of set.
MASCARENAS: Linda and I are working on a
fund balance policy, there isn’t one. That’s something we’ve been looking at,
pretty regularly. There’s no real silver bullet or recommendation.
DOTY: There’s no equation for it.
MASCARENAS: Yeah
DOTY: All it does, it gives you
protection on one side, but it also gives you a level of transparency, too, so
everybody knows that you’ve taken the insight to look down the road.
MASCARENAS: Yeah, absolutely.
MCNALLY: You can take that surplus and
move it into that capital improvement fund that you guys established for
buildings.
MASCARENAS: Correct
MCNALLY: At the end of the year.
MASCARENAS: Correct, right so you’re not
funding it from the fund balance, there’s lots of things.
MCNALLY: There’s a lot of ways to do it.
DOUGAN: So, of some of the stuff that we
went through, for example, the improvements to the former Probation Building or
the former Sheriff’s Residence are in really coming out of the capital funds.
DOTY: Right
DOUGAN: Some of that is actually coming
out of what was the sale of the old Kurtz’s Building, which we moved into the
fund, but a lot of these little things. The annual mini-split replacements, the
circulator pump replacements, all those projects that you see are $20,000.00 or
less, but still need to get done are carried in this year’s budget. So, I have
around, in Buildings & Grounds, I have around $160,000.00 - $180,000.00
that we just keep carrying forward and I am doing different projects with that
same dollar amount, but the other things in this budget, that they were
specifically budgeted, but they’re coming out of the capital.
DOTY: Right.
MCNALLY: But, I think what he was trying
to say was, you’ve got a $160,000.00 in the general budget, allocated every
year for these little projects, if you only spend $130,000.00, next year, you
don’t want to lose that in the next year, so we want that money to go
someplace, so we have access to it the following year with the additional
$160,000.00, so you can keep your budgeting every similar, but you don’t want
to fall behind.
DOUGAN: Yup, exactly.
MCNALLY: And a lot of times you can’t
spend the money in the given year, because the project’s not ready or something
like this, so, we don’t want to lose that money into the fund balance.
DOTY: Exactly.
MCNALLY: We want to be able to move that
at the end of the year for capital improvement, so we still have that money for
next year and next year we may spend $190,000.00 and not $160,000.00.
MASCARENAS: And if they’re ready to go,
we encumber it.
MCNALLY: Right
MASCARERNAS: Going into the following
year.
HUGHES: Is that a recommendation by Jim,
is that a Board decision, is that Mike?
MASCARENAS: You see a lot of those
housekeeping items. I say that a lot, when you see a resolution coming to the
Board that says, we want to carry over these funds for this purpose and this is
what’s happening, you see a lot of that in the first quarter of the new year
that happens.
HUGHES: Right
MASCARENAS: So, if it wasn’t spend in
that year, not specifically budgeted, absolutely has to come back to the Board,
if not, what happens, after you close up the books, any leftover funds to go
back to general. So, if it’s not otherwise specified by the Board in terms of
some type of action, it does revert back to fund balance, once you close your
books in a prior year.
MCNALLY: This all comes back to one
thing, you want consistent budgeting, year to year.
MASCARENAS: Absolutely.
MCNALLY: Mike, has done a great job over
the last couple of years keeping us on that path and we just don’t want to lose
$30,000.00-$40,000.00 out of this. It goes across the whole county line, too.
So, we can encumber or we can put it in a capital fund, if there’s one
established.
MASCARENAS: Right, because in a bad
budget year, there’s a real likelihood that you look at that money and you say,
that’s an easy cut.
MCNALLY: It is
MASCARENAS: Getting it back in is almost
impossible and that’s where you start seeing the problem start to occur.
DOTY: And that’s really my bottom
line.
MCNALLY: Once it’s gone, it’s hard to
get back.
MASCARENAS: It is.
MCNALLY: Anything else? We have a Public
Meeting at 9:30.
We are adjourned.
AS
THERE WAS NO FURTHER BUSINESS TO COME BEFORE THIS BUILDING AND FACILITIES TASK
FORCE, IT WAS ADJOURNED AT 9:50 AM
Respectively Submitted,
Dina Garvey, Deputy Clerk
Board of Supervisors