Buildings and Facilities Task Force
Monday, April 6,
2026 - 9:00 am
Chris Clark - Chairman
Supervisor Tyler called
this task force to order at 9:00 am with the following in attendance: Clayton
Menser, Tim Pierce, Richard Preston, Cathy Reusser, Matt Stanley, Meg Wood, Mike
Mascarenas and Jim Dougan. Chris Clark had been previously excused. Clayton
Barber was absent
Also present: Dina Garvey,
Andrew Stanley
TYLER: Alright, let’s
start this meeting of the Buildings and Grounds and I will officially turn it
over to Jim.
DOUGAN: Okay, we’ve got a
short update today, we were, remember we’ve been telling you that we were going
to do a presentation on pavement management, our whole process, but that will
easily eat up 35-40 minutes. So, we scrapped that and we’re just going to give
you a quick update, we’ll bring that next month, because you have the Public
Hearing that starts at 9:30 today, we didn’t feel like we have enough time. So,
Andrew, go ahead.
STANLEY, ANDREW: Alright,
just a quick update on the Ag and Youth Building. Cornell’s
scheduled to move in next week. The interior punch list is complete. There are
several items on the exterior that we need to address. Weather is looking like
to going to start coming our way, but not this week, hopefully next week they
can get out there.
DOUGAN: We are actually
going to issue the keys to Cornell, this week and Buildings and Grounds is
going to assist them, actually starting towards the end of this week. They’re
going to start moving things over slowly and then their whole phone system
moves on Thursday of next week. So, by the end of the week, Cornell is supposed
to be in. Soil and Water is moving in about the same time but haven’t told us
for sure.
TYLER: I have had a
couple of the people here in town asking to take a look inside. One of them is
a neighbor across the way, he used to be the Highway Superintendent, Wayne
Napper. He said we would like to go and take a look at it.
STANLEY: So, that is
pretty much where we are with that.
DOUGAN: Just a FYI, we
are building a schedule, too and we’re going to get that listed for the use of
that, we’re building a schedule for the use of the room in the basement, that
conference room.
TYLER: Yeah
DOUGAN: We’ve had a
number of quests already and so we’re going to get that and put that, probably
on the fairground’s website.
TYLER: I mentioned to the
Soil and Water Committee that we should have our first meeting there this
month, also.
DOUGAN: Yup
TYLER: Even if they’re
moved in or not, to have a meeting there.
MASCARENAS: Grand
opening?
DOUGAN: I wanted to make
sure that both of those parties were in there and then we were going to
schedule a grand opening.
MASCARENAS: Maybe mid to
late May, something like that.
DOUGAN: Yeah, we’re going
to try and get the agencies that help fund it involved.
MASCARENAS: Yeah, I just
want to invite the old Board, invite the new Board, people that had an awful
lot to do with that.
DOUGAN: Yup
STANLEY, ANDREW: Former
Probation Building: sheetrock and painting is complete. JFP, they’re in there
right now doing the acoustical drop ceiling, they should be done today. All the
materials for the flooring have been delivered. D & D is scheduled for
April 21 and 22 to have that complete. It should only take about a day; we got
two days blocked. Once the weather permits, JFP is going to begin on the
exterior concrete foundation, slab in the rear of the building, near the new
parking area that we’re going to install. HVAC mini-split materials, they’re
onsite and Buildings and Grounds have been installing for the last two weeks.
MASCARENAS: And you’ve
got conduit run.
STANLEY, ANDREW: Yup,
there’s conduit in the slab. Hugh had that installed so that way we could run
those line sets underground, basically through the conduit.
DOUGAN: We installed some
spares, so those will be out beyond that foundation. We got the new exterior
doors on the back installed since our last meeting and have installed the
replacement windows on the Personnel side of things.
REUSSER: I’m not on this
committee, but I am very interested. Do you have remote access to your HVACs?
Will you use software to monitor remotely when we’re in some kind of whatever?
STANLEY, ANDREW: I do not
believe that that building is set up for that.
DOUGAN: Not this
building.
PIERCE: I notice this
again this winter and it’s something for winter; do you have any process to
keep an eye on that far corner? I just remember an incident that happened 30
years ago. Rick Carpenter and I were walking back from the building and had
taken 2 steps and that whole sheet of ice from the high spot came down right
behind us and would have killed us. I wanted to mention it as it’s a bit of a
concern.
DOUGAN: Part of our
second floor renovation which we didn’t really talk about, but the second floor
is mostly demoed out. All the non-structured walls, if you were in there, it
was all cut up. They just added and added and added and it was, it was a nice
little maze.
MASCARENAS: It was weird.
DOUGAN: But we removed
all those and part of our process up there is going to be adding some more
insulation before we close it back up.
MASCARENAS: Yeah, just so
the Board understands, too, this isn’t the only project that is going to happen
there. This is, I would call this Phase One of the former Probation Building.
So, when we have a contractor come back and do an acoustical ceiling in another
section and somebody is going to say, wait you just did that. No, we did it in
this section, we’re dealing with the lower half of the building right now,
we’re kind of taking what we have budget-wise and working with departments that
want to work with us in creating that space and then we’re going to go from
there.
STANLEY, ANDREW: It’s
really only like 2/3rds of the first floor, too.
MASCARENAS: Exactly
TYLER: Thanks for the
head’s up on that Tim.
MASCARENAS: And Cathy,
I’ve always been a little leery of controls. We had a company come in here
years ago, wanted us to run controls on all of our buildings through here.
Danforth did ours back then and the problem with controls that I find is you
get into same issues that you get into with everything else. There’s a life
expectancy with those types of things and you get into propriety and then
you’re dealing, sometimes with a programmable thermostat on the wall will
handle, will save you for $7-$8, will save you thousands, if not millions over
the long term. There are some nice things about controls, but you can count on
having a bill every 5-7 years for all the upgrades and maintenance and it’s
only as good as the people that are trained on using them, too. So, what you
find is, yeah, we have that ability, but nobody’s really using it.
REUSSER: What I like at
the residential level is that I can be in Florida, and I can see what the
temperature of my house is and if it’s real cold, I
can kick up my heat pumps.
MASCARENAS: Yup, we do
have those alarm systems like in Public Safety, right Jim?
DOUGAN: Yes, we do and in
some of our bigger buildings we do have controls, but we’re trying to keep
them, not as a full building automation system, but a little simpler and as you
know at the Public Safety Building, we’re trying to get away from propriety.
We’ve been stuck with a company for controls at the Public Safety Building for
its entire life.
REUSSER: Do we have
nightwatchmen that go around and do that sort of thing?
MASCARENAS: We do, we
have staffing here, pretty much 24-7, some gaps, but not a lot.
REUSSER: Nothing
dangerous.
MASCARENAS: Yeah
DOUGAN: This particular
building has a propane fired baseboard heat, but the mini-splits that we’re putting in they’re electric,
but they’re electric, both heating and cooling. So, if for some reason that
boiler went out, you still have those as a backup for heating.
STANLEY, ANDREW: So,
pictures of where we’re currently at. That ceiling should be done by the end of
day. They really don’t have a lot left to do.
DOUGAN: Buildings and
Grounds will start putting lights in. You’ll see the mini-splits is on the wall
in both of those pictures there. They’re well on their way. The trim is here to
start trimming out the windows and doors. We did talk about those conduits
already and so.
MASCARENAS: And our guys
did the lion’s share of that work, just so everybody’s aware. What we
contracted out was the taping of the sheetrock and the ceiling.
STANLEY, ANDREW: So,
H&T has provided about a 75% set of engineering drawings for the parking
area and the drainage in the back. They’re expected to have us 100% by the end
of this month. Just got a couple of comments back to them and they’ll clean it
up and get them a little more closer to construction grade.
DOUGAN: Once we do that,
we’ll put that out to our 4 civil term contractors to do the sidewalk work, the
concrete curve work and the prep work and then we’ll probably pave it and line
stripe it ourselves. It will be our plan of attack for a little later this
year.
MASCARENAS: Yeah, the
thought process for the backside of that building for that work is really
trying to get together, not only access, but a loading dock. We get large
deliveries, as you can imagine, and there’s no place to put it. A lot of time
it gets set out in the parking lot, regardless of the weather. You’ll have
whoever’s available, run around out there, trying to get stuff inside.
DOUGAN: It was me on
Thursday night.
STANLEY, ANDREW: Just a
quick update on Frontier Town. The contract with Aubertine and Currier has been
executed and they’re going to begin their survey and building assessment, as
soon as the weather permits. So, as soon as the snow
is off the ground in North Hudson, they will all be there.
MASCARENAS: Will that
project be completed this summer?
DOUGAN: No, we’ll have a
report, we’ll have recommendations. We should have drawings, but I don’t think
you’ll actually have restored any of the buildings by the end of the year.
MASCARENAS: Okay
DOUGAN: I think we’ll
have stuff by Fall, we might be able to bid it, but I don’t think. I think
weather will try on us before restore.
STANLEY, ANDREW: New
Project, Transportation Facility: draft RFQ has been sent to DOT for their
approval. Once DOT has given their concurrence on it, an RFP will be advertised
for that.
DOUGAN: That, we had the
one meeting over at the new building and got the green light at looking to
relocating the campground area to allow this project to potentially go over
there. Our process has to follow NYDOT. They’re the ones funding it and like
Andrew said, we’ve got a request for qualifications that has to go out to DOT’s
list of 15 pre-qualified engineering/architecture firms and so they’re
reviewing that now and we’ll get that out shortly and then get somebody under
contract.
Yeah, I wasn’t able, like
I said, we chose not to do the pavement management program today, because of
the shortened meeting, but I did want people to see where our asphalt costs
have gone up. So, we bid asphalt in January. We also bid it based on, every
month DOT publishes an update on the cost of what’s called performance grade
debinder, that’s the liquid asphalt that goes into these asphalt mixes and so
that’s how your price is based throughout the year. So, in January it was $643
a ton for the liquid asphalt. In April it’s now $730 and then down below, we
have calculations for the different types of mix that we put down. How much
liquid asphalt is in it, along with, there’s in NYDOT typical manual, there’s
an adjustment for fuel and am adjustment asphalt. So, that $6.26 is how much
per ton, buying Type 6 asphalt top, which is something that a lot of your towns
will choose to use, that’s how much it went up since January.
MASCARENAS: Jim, if you
were to consider your CHIP funds.
DOUGAN: Yup
MASCARENAS: How much less
can you blacktop?
DOUGAN: For me, based on
that number right there, it’s probably 2 miles that it’s going to cost us. Now,
we did, in our first projection, we did project a $2/ton increase, because we
know that early in the year it goes up when travelling season gets here. We all
know gas prices go up there, but we did project $6.26, but we’ll be looking at
it closely. We’ll see what it does throughout the reason, it changes every
month.
MASCARENAS: Yeah, I can
see that.
DOUGAN: I’ll be able to,
you can see 2025/2024/2023.
MASCARENAS: Yeah, that’s
what I am looking at, 2025, you’re talking $109 difference that’s pretty
significant.
DOUGAN: It eats it up; it
eats it up real quick. So, we’ll have to look at what’s on our list and decide which
was the least in need for this year.
MENSER: Along those
lines, I talked to our Highway Superintendent, last week about it and he’s
going to attempt to push out the timeframe of when we’re going to do asphalting
for the town, hoping that maybe once we get done playing in Iran that prices
come back down.
DOUGAN: Yeah, there’s a
real fine line there. If everybody’s doing that and the asphalt plant isn’t
going to produce it for you, what we found and this is, honestly, you’re
walking right into my pavement management discussion. We try really hard to
push out as much asphalt that we can in the months of May and June, because
it’s usually in July and August that the State is getting asphalt from those
same plants, and so they’ve got every truck and DOT came out with something
new, a year ago, 18 months ago called warm mix asphalt, instead of hot mix
asphalt and when they’re producing that, you can’t get any of the hot mix out
of the plants. So, we do as much as we can in May and June. You’re right, if I
could hedge my bets and play with the costs, but I am not sure, I don’t know if
it’s going to help me or not, it’s a real fine line.
MENSER: Yeah, we’re not
sure either, but that’s what we’re considering.
TYLER: And when the State
starts getting theirs, like you said, nobody else can get it.
STANLEY, ANDREW: Yeah,
they shut us right off.
TYLER: Last year, we had
to shut down in Westport, because we wanted to do a project.
STANLEY, ANDREW: Yeah, it
makes it very difficult. Even if we were willing to put down warm mix, you
know, chances of us getting enough material for a project is unknown.
STANLEY, MATT: In
November
MASCARENAS: We do pave in
November. Is the warm mix as durable?
STANLEY, ANDREW: The warm
mix, so DOT implemented that through the Green Initiative. It’s supposed to be,
you know, less fuel to make the product. Is it more durable? No. It’s hard to
put down. They claim it’s just as durable as the hot mix, but.
MASCARENAS: Time will
tell, right?
STANLEY, ANDREW: Yeah,
it’s supposed to be greener, basically.
MASCARENAS: And if you do
a road with CHIPS, it’s got to last how long?
DOUGAN: 10 years, a
minimum of 10 years and we’re just for interested in being a Guinea Pig, up
here to be honest with you. They haven’t touched enough to know.
STANLEY, ANDREW: That and
the cost, too, because there’s so many chemicals, plasticizers added to that to
compensate for the loss of heat, basically that it just drives the cost up.
DOUGAN: Is it really
green? When you start putting all that stuff in there.
STANLEY, MATT: And not to
prolong the asphalt discussion, but the cost is even going to go up if we’re
hiring to have the materials trucked to us?
MASCARENAS: Correct
STANLEY, ANDREW: Sure
STANLEY, MATT: Because
the prevailing wage is affecting that this year?
DOUGAN: The prevailing
wage rate, yes, I have been telling you, partially because they are now paying
it even if you’re empty. The previous law said hauling of aggregate and
Department of Labor, who regulates prevailing wage rate didn’t come out and say
that asphalt was aggregate. Now I don’t know how, but they didn’t, so okay we’re
happy with that. They have now cleared that up and say asphalt is aggregate and
you’ve got to pay it whether your truck is full or whether your truck is empty.
So, that has increased the price, probably about the same amount as the new
Federal Highway’s Administration’s law that you have to go through entry level
driver training, which has cost us a lot of truck drivers.
STANLEY, ANDREW: And
adding to that, a little bit back, with buildings, concrete has dodged that
law, currently, but that’s probably coming down the line also.
DOUGAN: And so, honestly
the law doesn’t affect towns that are outside of Essex County as much as it
affects all of us. We don’t have a single asphalt plant in the County. Every
time we’re hauling it, we need a lot of trucks to get, we can pretty easily on
most of our roads we could put down 1,500 tons a day, it wouldn’t be hard. It’s
about getting the trucks and getting rounds of trucks there. But if you’re
hauling all of it a tandem versus a triaxle versus a Flow Boy, the hard part
there is how many tandems do you have to put on the road to get you enough
asphalt where it’s worth a day’s worth of the paving crew. That’s why we bought
a Flow Boy. That’s why we’re trying to haul more with triaxles when we can or why
we still continue to use hired trucks if they’re bringing us a Flow Boy,
because we’re getting 33 tons instead of 18, you know almost double.
TYLER: Alright, anything
else?
DOUGAN: We’ll get into
more detail on that. Just a couple of other things, we did get the bids for
carpet across the hall, once Personnel moves over to the former Probation
Building. Our bids for the County Attorney and Real Property’s big room and the
clinic room and a bathroom over at Public Health are all out. The septic system
materials for over at Public Health are just about to go out to bid. The
mini-splits for the Public Safety Building that we do annually, those are
already done and some of the grant funded work over at the Public Health
Building, remodeling some of the bathrooms, we now have those drawings done. We
got that coordinated for code for handicapped accessibility and those will be
going to the general construction term contract, here in the next month, as
well. So, just a number of other things that are going on other than these big
hitters.
TYLER: Thank you.
PIERCE: Just one last
comment, I won’t speak for the Board for the Town of Lewis, but I don’t believe
that we’re going to be in a position to move forward with purchasing the old
Cornell Building. I will know more after the next meeting, but I don’t think so
and I wanted to give you the heads up there.
MASCARENAS: I appreciate
that, thank you.
TYLER: Anything else from
anybody? Alright, we will move onto our next meeting. We are adjourned.
AS
THERE WAS NO FURTHER BUSINESS TO COME BEFORE THIS BUILDING AND FACILITIES TASK
FORCE, IT WAS ADJOURNED AT 9:25 AM
Respectively Submitted,
Dina Garvey, Deputy Clerk
Board of Supervisors